Project Scope
Secured via competitive tender.
Phase 1 works comprised the renewal of 36 nr kitchens including:
installation of new Mechanical Heat Recovery and Ventilation units plus
ductwork.
Associated works involved renewal of all ceiling, wall and floor finishes, reconfiguration of partition walls
supply and installation of new dining furniture.
All installations were completed whilst flats remained in occupation, with 9
kitchens being completed every 9 working dates. Successful completion of Phase 1 on time and within budget led to negotiation of a second phase
consisting of a further 90 nr kitchens over a 30 week rolling programme,
again undertaken whilst all students remain in occupation.
Property Details
Kitchens
Bedrooms
Bathrooms
126
0
0
Duration
36 Weeks
Property Type
Student Accommodation
Property Location
Glasgow, UK